Project Workforce Operations · Allocation ledger

Give each hour one place to go.

Start with available time, then decide which project gives way. The filled case below keeps Ana's paid employment commitment separate from the hours available for delivery. These are fictional planning inputs for an adult desk-based employee in England with a 40-hour daytime agreement and unrestricted internal budgets.

The decision: 40 paid hours less 8 hours of leave and 4 hours of shared work leaves 28 project hours. A needs 16 and B needs 20. With A first, allocate A 16 and B 12; defer or reassign 8 B hours. An EOR cannot make both deadlines fit the same person.

Read the assignment and authority guide · Compare employment support for this decision

1. Define one paid week
2. Keep employment authority separate

These are user-entered case facts. A tick does not establish permission, employee agreement, compliance or completion. Check the underlying employment record. Unknown impact belongs in the proposed-change pathway until resolved.

28 project hours. 8 hours of demand must move.

Keep 16 hours on A and 12 on B. Defer or reassign 0 A hours and 8 B hours; the programme owner must accept the resulting delivery plan.

40 paid hours − 8 leave − 4 shared work = 28 project hours. Demand: 36 hours. Unallocated paid time: 0 hours.

Allocation arithmetic does not authorise a new duty, change pay or end employment.

Internal allocation of the paid week and £1,600 envelope
CategoryHoursShare of allocated project timeShare of paid weekAllocated cost
Project A1657.14%40%£640.00
Project B1242.86%30%£480.00
Shared work4—10%£160.00
Paid leave8—20%£320.00
Unallocated paid time0—0%£0.00
Paid commitment40100%100%£1,600.00

Cost follows hours divided by contracted paid hours. The project-only percentages use a different denominator. Neither share changes pay, invoice terms or legal cost eligibility.

Export downloads the current inputs, calculated ledger, open holds and export time. Nothing is saved automatically or sent anywhere. Keep the employment evidence with the exported record; this tool cannot verify it.

What changes the answer?

Close the record

Publish one dated task schedule, name the programme owner who accepts the deferred work and identify the expense owner for each project. Attach any employer outcome separately. At the weekly close, reconcile actual hours and expenses against the plan; correct the allocation ledger without retrospectively inventing approval for different work.